Post filled under : Goddard School Project

Post filled under : Goddard School Project

Goddard School Update – August 17, 2012

August 17, 2012

Here is the latest update photo from the Goddard Preschool Project in San Ramon, CA.      

Filled under : Archives , Goddard School Project

Goddard School Project UpdateAugust 10, 2012

August 10, 2012

Here is a progress photo from the week ending August 10, 2012 on the Goddard School Project; a new 8,000 SF, preschool located in San Ramon CA at Gale Ranch.      

Filled under : Archives , Goddard School Project

Goddard School Update August 3, 2012

August 4, 2012

We’ve made some great progress on the new Goddard Preschool this week. Wall framing – Complete

Filled under : Goddard School Project

Goddard School Update July 27, 2012

July 27, 2012

One more photo update for Goddard Pre-school for the week.  Framing is already underway on the school! July 27, 2012  – Framing in Progress.  Construction site photography by Proforma Construction

Filled under : Archives , Goddard School Project

Goddard School Construction Update Week Ending 7/26

July 26, 2012

Goddard School Progress Update – Week Ending 7/26 Progress of the 8,000 square foot Goddard Pre-school located in San Ramon –          Moisture barrier and wafflemat complete –          Reinforcing –          Pour slab –          Start layout Construction site photography by Proforma Construction  

Filled under : Archives , Goddard School Project

Goddard School Progress Update

July 26, 2012

Goddard School Progress Update – Week Ending 7/19 This will be a new 8,000 SF, preschool located in San Ramon CA at Gale Ranch. –          Moisture barrier, waffle boxes started –          Dig sewer –          Grease trap for trash enclosure, site sewer –          Site sewer, back-fill fire line –          Dug … Continue reading

Filled under : Archives , Goddard School Project

Underground

July 11, 2012

Proforma starts the underground sewer and electrical trenching for this new 8,000 square foot preschool

Proforma Groundbreaking

July 9, 2012

Proforma Construction announces the groundbreaking of the new Goddard School. A new 8,000 SF, preschool located in San Ramon CA at Gale Ranch. Construction begins July 2012, and will be ready to open in December.” Goddard Schools is a franchise entity. Proforma is the design build contractor.       … Continue reading