Blog

Goddard School Progress Update

by Proforma Construction Inc, July 26, 2012

Goddard School Progress Update – Week Ending 7/19

This will be a new 8,000 SF, preschool located in San Ramon CA at Gale Ranch.

–          Moisture barrier, waffle boxes started
–          Dig sewer
–          Grease trap for trash enclosure, site sewer
–          Site sewer, back-fill fire line
–          Dug domestic water
–          Water & site underground completed, soil exported

 

http://proformaconstructioncalifornia.com http://proformaconstructioncalifornia.com http://proformaconstructioncalifornia.com http://proformaconstructioncalifornia.com

http://proformaconstructioncalifornia.com

Proforma at Work

Construction site photography by Proforma Construction